Visteon Corporation
Troy, MI
Developer/Landlord:
Oakland Park IX, LLC
Architects:
Ghafari Associates, LLC
Dearborn, MI
Biddison Architecture and Design
Farmington Hills, MI
Construction Manager:
Roncelli, Inc.
Sterling Heights, MI
Size:
220,000 SF
Building Use:
Manufacturing Facility
Visteon Corporation
The wall was constructed of structural steel columns at 25 ft. on center, inserted between the building’s existing columns along with horizontal steel channels at 7 ft. on center. New pre-finished metal siding was affixed to the structural steel framing. All necessary tie-ins to the roof, floor and end walls were performed to facilitate removal of the wall.
RB Construction’s long standing relationship with the steel supplier resulted in the attainment of two weeks of accelerated schedule delivery, meeting Visteon’s critical milestone date to provide conditioned space for their temperature sensitive equipment and materials.